|
It is generally well recognised that when concrete has to be mixed and placed in either very hot or very cold weather, it is necessary to take precautions to ensure that the concrete is not damaged or adversely affected
by the ambient weather conditions. At temperatures below freezing, for example, freshly placed concrete may be damaged by the formation of ice within its pore structure. In
very hot weather the concrete may stiffen prematurely, preventing it from being compacted and finished properly, or the temperature of the concrete may rise to the point where thermal cracking occurs as it cools. It is perhaps not so well recognised, however, that even at moderate air temperatures, strong dry winds can cause concrete to dry out prematurely and to crack.
There are a few fixed rules on what constitutes hot or cold weather in respect of concreting operations. NZS 3109 Concrete Construction discusses the range
5°C to 30°C and AS 1379 The Specification and Manufacture of Concrete
to be within the range of
5°C to 35°C at the point of delivery. Precautions will always be necessary when ambient air temperatures lie outside this range.
They may well be necessary, however, at air temperatures within this range, at less than
10°C or more than 30°C, say. At the lower temperatures, the concrete, whilst in no danger of freezing, may take an excessively long time to gain its specified strength. At the higher temperatures, particularly if accompanied by hot dry winds, plastic cracking and premature
stiffening of the concrete may take place.
Concreting in Hot Weather
The effects of high temperatures can be summarised as follows:
- Shorter setting times and early stiffening
- Increased rates of hardening
- Possible 28 day strength loss
- Increased tendency for plastic shrinkage
- Difficulties in placing and finishing
- Danger of cold joints - a cold joint is formed when plastic
concrete is placed against concrete that has set and commenced
hardening
Precautions for hot-weather concreting should be initiated
when the ambient temperature is expected to exceed 30 to
35°C. These precautions may consist of one or more of
the following practices:
- Dampening forms, reinforcement and subbase
- Erecting wind breaks and sunshades to protect exposed
concrete surfaces
- Cooling concrete ingredients
- (During transport of wet concrete) cooling containers,
pipelines, chutes, etc
- Completing the transporting, placing and finishing of
concrete as rapidly as is practicable
- Informed usage of set-retarding admixtures (to counter
premature stiffening of the fresh mix)
- Immediately following the initial finishing operation,
spraying a fine film of aliphatic alcohol over the exposed
concrete surface - to limit evaporation and help control
plastic shrinkage cracking (this should be repeated as necessary
during any subsequent operations up to final finishing)
- Immediate curing after final finishing is complete
- Moist curing to control concrete temperature
- Restricting placing to night time when ambient temperatures
are generally lower.
Concreting in Cold Weather
The prime effects of low temperature on freshly placed concrete
are:
- A decrease in the rate at which the concrete sets and
gains strength, with a resultant increase in the time taken
to finish the concrete;
- (at temperatures below freezing) physical damage to the
concrete in the form of surface scaling or bursting, and
the cessation of hydration.
Precautions which may be taken to protect the concrete
in cold weather may consist of one or more of the following
practices:
- Providing heaters, insulating materials, and enclosures
if sub-zero temperatures are expected
- Using high-early-strength cement
- Heating the raw materials (the temperature of the concrete
when it is placed in the forms should be above 5°C)
- Not placing concrete on frozen ground
- Ensuring means of maintaining suitable curing temperatures
(when using Type GP (general purpose portland) cement the
temperature of the concrete should be maintained at 20°C
or above for 3 days
- Insulating the concrete (a thick insulating blanket is
often sufficient protection for pavements)
| Controlling
the effects of hot and cold weather |
| Aspect |
In Hot
Weather |
In Cold
Weather
|
Preplanning
|
Preplan
carefully to avoid delays at all stages.
Have standby equipment and
manpower for all stages.
Pay particular attention to speed of application,
effectiveness and duration of curing arrangements.
Schedule nighttime placement
if possible. |
Preplan
carefully to ensure adequate equipment and manpower
available especially if there is a likelihood of
temperatures below 0°C.
|
| Concrete |
Use water reducing retarding
admixtures in the concrete.
Reduce the temperature of the concrete by (in order
of effectiveness):
- reducing temperature of aggregates
- using liquid nitrogen injections in the mixed
concrete
- reducing temperature of mixing water
- using cement with lower heat of hydration
- reducing temperature of cement
|
Reduce the setting time of the
concrete by (in order of effectiveness):
- heating mixing water
(maximum 70°C)
- using (chloride-free)
accelerating admixture
- using higher cement content
- using high-early-strength
cement
|
| Batching,
mixing and transporting |
Shade batching, storage and
handling equipment or at least paing with reflective
paint.
Discharge transit mixer trucks as soon as possible.
|
Placing
and Compacting
|
Shade reinforcement, formwork and
subgrades if possible and spray with water.
Ensure that slabs have minimum 'fronts' to which
concrete is added.
Place concrete in walls and deep beams in shallow
layers.
Use burlap covers if there is any delay between load
deliveries.
|
Thaw frozen subgrades and heat
frozen forms (particularly steel) before placing
concrete.
Warm, insulate or enclose handling and placing
equipment.
Avoid delays in handling and placing.
|
Finishing
and Curing
|
Use sunshades and windbreaks to
lengthen finishing time (or, if hot/dry winds present,
to control plastic shrinkage cracking).
For flatwork, use aliphatic alcohol after initial
screeding if hot/dry winds present.
Use revibration to correct plastic shrinkage
cracking.
Use water curing as the preferred method for at
least 24 hours.
|
Maintain concrete temperature
until safe strength reached by means of form insulation,
insulated covers or heated enclosures.
Delay striking of formwork for as long as
possible.
Avoid thermal shocks and temperature variations
within a member. This includes not using cold water for
curing, and removing protective measures
gradually.
|
|